پتروشیمی دهلران

🔻 Purpose: Control System for control of two chillers, two Refrigerant Dryer, two PSA Nitrogen Generator & 1 Desiccant Dryer with Heater

🔻 Description: Redundant CPU, Redundant Power, Redundant 10 Siemens S7- 400H Control System with Remote 10 Racks and 5 cabinets with PC-Panel as EWS/OWS Redundant Modbus/TCP Communication

🔻 Client: Dechlorane Petrochemical

🔻 Consultant/ Main Contractor: EIED

🔻 Year: 2019